The Fámjinstunnilin finish 25.06.2025

  • oko
  • Jun 25
  • 1 min read

The Fámjinstunnilin is safety approved and will open for public today 25.06.2025.

The Fámjinstunnilin is located in Suðuroy, between Fámjin and Øravík. The tunnel is just above 1200 meters long. FAT was held in El-Service and approved 7th April, and the safety equipment was approved 20th June.

We have installed lights, emergency lights, battery backup system, SCADA safety system,17 emergency stations, with emergency phones and fire extinguishers.


There are 2 safety control rooms are located outside each portal, where personnel can control the safety inside the tunnel.

The safety equipment is controlled by a Alarm and Control System from El-Service. This system is also beeing used for most of the other tunnels in the Faroe Islands.




We wish all in Suðuroy, and in Fámjin congratulations and safe journey thru the tunnel.




 
 
 